Wellsite Supervision & Management

Ammerlaan Tie-back installation

Project Description

Ammerlaan Geothermie commissioned a workover on wells PNA-GT-05-S1 (producer) and PNA-GT-06-S3 (injector) to install new tieback strings as part of a long-term well integrity strategy. The objective is to create a second independent mechanical barrier and a monitorable annulus to enable early detection of integrity loss through annulus pressure monitoring, and to isolate the primary well envelope from production fluids.

Operations were planned for continuous execution (24/7) and combined rigless intervention (RIU), wireline, and hydraulic workover (HWU) activities to complete tieback installation and related wellhead reinstatement activities.

Challenges

  • Designing the tieback to support long‑term integrity monitoring via a reliably monitorable annulus.
  • Managing different integrity objectives and material selections for the producer and injector within one coordinated operation.
  • Planning safe rig movements and equipment layout on a compact location, surrounded by active greenhouse facilities.
  • Integrating rigless intervention, wireline and hydraulic workover phases into one continuous 24/7 operation.

Role of WEP

Following the acquisition of the former Veegeo activities from Sproule, GST is responsible for the end-to-end engineering and execution of the tieback installations, translating well integrity objectives into a safe, coordinated workover strategy covering design, planning and on-sites supervision.

Overview

  • Client
    Ammerlaan Geothermie B.V.
  • Location
    Pijnacker, the Netherlands
  • Well
    PNA-GT-05-S1 & PNA-GT-06-S3
  • Date
    Start: 29 June 2026
    End: 17 July 2026
  • Objective
    Tieback installation for Ammerlaan’s PNA-GT-05-S1 & PNA-GT-06-S3 geothermal wells to strengthen long-term well integrity with monitorable annuli.
  • Depth
    Depth (MD):
    Depth (TVD):

View project on the map

Name
PNA-GT-05-S1 & PNA-GT-06-S3
Description
Tie-back installation (WO & Integrity upgrade)
Start
June 29th, 2026
End
July 17th, 2026
Ammerlaan Geothermie commissioned a workover on wells PNA-GT-05-S1 (producer) and PNA-GT-06-S3 (injector) to install new tieback strings as part of a long-term well integrity strategy. The objective is to create a second independent mechanical barrier and a monitorable annulus to enable early detection of integrity loss through annulus pressure monitoring, and to isolate the primary […]